 Concerns as to the state odf the site continue: the concrete slab (2 metres thick) is still intact. Does this conform to the requirements of the permit issued by Moreland Council?
 
Dear Mr Collins - the demolition company working on the old Coburg High School site informed me today that they had completed their work at […]

150 days since demolition permit expired

Today is the 150th day since the demolition permit issued by Moreland ocuncil was due to expire. Work continues on the site with no end in sight. The major issue currently is the destruction of Rodda Street by the heavy vehicle traffic into the site removing debris.

 
Dear Mr Robertson,

I refer to your recent e-mail of 2 January 2008 to Roger Collins, Director City Development. An inspection of the former Coburg High School site confirms that since Council’s last correspondence to you of four or so weeks ago the demolition works on the site have been substantially completed. Council is currently awaiting advice from the site owner […]